40 Eastbourne Terrace, Hotel, London, W2 6LG

PROJECT OVERVIEW

Mandolite CP2 fireproof spray to existing hollow pot slabs, internal partitions, wall linings, insulation works, ceilings, passive firestopping bulkheads and skimming as part of the construction of a 369 room Premier Inn.

KEY STATISTICS
  • Construction Methodology – Refurbishment to existing basement to level 03 with new build works to levels 04 & 05.
  • Value – £5,000,000
  • Project Duration – 52 weeks
  • Main Contractor – Gilbert Ash